IT129Knowledge Management Datamart
Details
This project has a pattern selected. Click regenerate to (re)build phases + role demand from the pattern — this replaces current phases, demand, and any manual FTE adjustments.
Phases & role demand
Initiating2027-02-01 → 2027-02-10
Role demand (FTE)
Planning2027-02-11 → 2027-03-02
Role demand (FTE)
Executing2027-03-03 → 2027-04-25
Role demand (FTE)
Deploying2027-04-26 → 2027-05-13
Role demand (FTE)
Closing2027-05-14 → 2027-05-31
Role demand (FTE)
Dependencies
Predecessor projects that constrain when this project can start or finish.
FS finish-to-start (default) · SS start-to-start · FF finish-to-finish · SF start-to-finish. Lag is in months (negative = lead).
None.