Level load

Priority-ordered greedy scheduler. Capacity per role×month comes from each role's Pool FTE (set on Roles); named resources are a separate staffing concern and are not part of this solve. For each project (highest priority first) the solver honors upstream dependencies plus lag, then shifts start month rightward by the minimum amount that clears any capacity overage — subject to the project's target-complete date. Projects that can't fit are listed with the specific bottleneck.

Role × Month utilization (post-solve)

RoleJan 26Feb 26Mar 26Apr 26May 26Jun 26Jul 26Aug 26Sep 26Oct 26Nov 26Dec 26Jan 27Feb 27Mar 27Apr 27May 27Jun 27Jul 27Aug 27Sep 27Oct 27Nov 27Dec 27Jan 28Feb 28Mar 28Apr 28May 28Jun 28Jul 28Aug 28Sep 28Oct 28Nov 28Dec 28Jan 29Feb 29Mar 29Apr 29May 29Jun 29Jul 29Aug 29Sep 29Oct 29Nov 29Dec 29Jan 30Feb 30Mar 30Apr 30May 30Jun 30Jul 30Aug 30Sep 30Oct 30Nov 30
PM (Project Manager)0.5/24.01.3/24.01.4/24.01.7/24.02.8/24.02.9/24.04.5/24.05.0/24.06.0/24.06.9/24.07.6/24.07.6/24.07.0/24.07.5/24.08.6/24.07.8/24.08.0/24.07.3/24.06.7/24.06.8/24.06.6/24.05.3/24.05.4/24.07.3/24.06.9/24.05.4/24.05.1/24.05.1/24.04.6/24.04.0/24.03.7/24.04.7/24.04.6/24.04.1/24.03.8/24.03.5/24.02.5/24.03.9/24.04.1/24.03.8/24.03.5/24.03.4/24.03.6/24.04.1/24.03.9/24.03.6/24.03.4/24.03.3/24.02.4/24.02.0/24.02.6/24.03.1/24.03.0/24.02.9/24.02.9/24.02.8/24.02.5/24.02.0/24.01.1/24.0
BA (Business Analyst)0.4/6.01.1/6.01.2/6.01.3/6.02.1/6.02.2/6.03.5/6.03.8/6.03.7/6.03.9/6.04.2/6.03.8/6.03.4/6.03.6/6.05.2/6.03.9/6.03.9/6.03.9/6.03.1/6.02.7/6.02.7/6.02.4/6.02.1/6.03.6/6.03.2/6.02.2/6.01.7/6.02.9/6.02.3/6.01.7/6.01.3/6.03.0/6.02.7/6.01.9/6.02.1/6.01.4/6.00.9/6.02.8/6.02.8/6.02.1/6.01.8/6.01.7/6.01.9/6.02.5/6.02.0/6.01.7/6.01.3/6.01.1/6.00.9/6.00.8/6.01.1/6.02.4/6.02.1/6.01.8/6.01.6/6.01.2/6.00.7/6.00.2/6.00.0/6.0
EA (Enterprise Architect)0.3/11.00.9/11.00.9/11.01.8/11.02.3/11.02.6/11.04.0/11.04.3/11.04.8/11.05.2/11.06.0/11.06.1/11.05.2/11.05.1/11.010.3/11.011.7/11.012.3/11.012.4/11.010.9/11.011.1/11.010.1/11.09.4/11.010.3/11.012.5/11.011.1/11.09.4/11.07.9/11.06.3/11.05.7/11.04.4/11.03.9/11.04.7/11.03.3/11.02.2/11.02.3/11.02.9/11.01.7/11.02.4/11.02.6/11.02.4/11.02.2/11.02.2/11.02.4/11.03.3/11.02.7/11.02.4/11.02.6/11.02.5/11.01.9/11.01.6/11.01.7/11.02.2/11.01.9/11.01.6/11.01.7/11.01.7/11.02.3/11.01.9/11.00.6/11.0
OCM (Organizational Change Management)0.1/3.00.3/3.00.4/3.00.6/3.00.9/3.01.0/3.01.6/3.02.1/3.02.4/3.03.2/3.02.8/3.03.7/3.04.4/3.03.5/3.03.2/3.03.4/3.04.6/3.04.1/3.02.7/3.03.8/3.04.2/3.02.9/3.02.5/3.03.8/3.05.3/3.02.5/3.03.7/3.02.9/3.02.9/3.02.7/3.02.9/3.03.1/3.03.1/3.03.0/3.02.6/3.02.4/3.03.0/3.03.0/3.02.9/3.02.3/3.02.9/3.03.0/3.02.5/3.02.7/3.03.0/3.02.7/3.02.0/3.03.1/3.03.0/3.02.6/3.03.6/3.03.0/3.02.9/3.01.7/3.01.8/3.02.1/3.01.5/3.02.7/3.03.5/3.0
Server Ops0.0/4.00.0/4.00.0/4.00.1/4.00.1/4.00.2/4.00.3/4.00.5/4.00.6/4.00.7/4.00.8/4.00.8/4.00.7/4.00.6/4.00.7/4.00.8/4.00.9/4.00.9/4.01.2/4.01.3/4.01.3/4.01.2/4.01.1/4.01.0/4.01.1/4.01.1/4.00.9/4.00.8/4.00.8/4.00.7/4.00.6/4.00.6/4.00.6/4.00.6/4.00.5/4.00.4/4.00.3/4.00.3/4.00.4/4.00.5/4.00.5/4.00.5/4.00.4/4.00.4/4.00.5/4.00.5/4.00.5/4.00.4/4.00.3/4.00.2/4.00.2/4.00.2/4.00.3/4.00.4/4.00.5/4.00.4/4.00.3/4.00.2/4.00.1/4.0
Storage Ops0.0/4.00.0/4.00.0/4.00.0/4.00.1/4.00.1/4.00.1/4.00.3/4.00.3/4.00.4/4.00.4/4.00.4/4.00.4/4.00.3/4.00.4/4.00.5/4.00.5/4.00.5/4.00.6/4.00.6/4.00.6/4.00.5/4.00.5/4.00.5/4.00.6/4.00.6/4.00.5/4.00.4/4.00.4/4.00.4/4.00.3/4.00.3/4.00.3/4.00.3/4.00.3/4.00.2/4.00.2/4.00.2/4.00.2/4.00.3/4.00.3/4.00.3/4.00.2/4.00.2/4.00.3/4.00.3/4.00.3/4.00.2/4.00.1/4.00.1/4.00.1/4.00.1/4.00.2/4.00.2/4.00.3/4.00.2/4.00.2/4.00.1/4.00.1/4.0
Cloud Ops0.0/4.00.1/4.00.1/4.00.2/4.00.4/4.00.5/4.00.6/4.01.1/4.01.5/4.01.7/4.01.9/4.01.7/4.01.5/4.01.3/4.01.3/4.01.5/4.01.5/4.01.4/4.01.3/4.01.3/4.01.2/4.01.1/4.00.9/4.01.0/4.01.5/4.01.5/4.01.3/4.01.2/4.01.3/4.01.2/4.01.0/4.01.1/4.01.3/4.01.4/4.01.3/4.01.1/4.00.7/4.00.8/4.01.1/4.01.4/4.01.3/4.01.2/4.01.1/4.01.1/4.01.2/4.01.3/4.01.2/4.01.0/4.00.7/4.00.5/4.00.5/4.00.6/4.00.9/4.01.1/4.01.2/4.01.1/4.00.8/4.00.5/4.00.3/4.0
DBA (Database Administrator)0.0/4.00.0/4.00.0/4.00.1/4.00.1/4.00.2/4.00.3/4.00.5/4.00.7/4.00.8/4.01.0/4.00.9/4.00.8/4.00.7/4.00.6/4.00.8/4.00.8/4.00.7/4.00.7/4.00.7/4.00.6/4.00.5/4.00.4/4.00.5/4.00.7/4.00.7/4.00.7/4.00.5/4.00.6/4.00.6/4.00.5/4.00.5/4.00.6/4.00.7/4.00.7/4.00.6/4.00.4/4.00.4/4.00.6/4.00.8/4.00.7/4.00.6/4.00.6/4.00.5/4.00.7/4.00.7/4.00.7/4.00.5/4.00.4/4.00.3/4.00.3/4.00.3/4.00.5/4.00.6/4.00.6/4.00.6/4.00.5/4.00.3/4.00.2/4.0
Network Ops0.0/4.00.0/4.00.0/4.00.2/4.00.3/4.00.3/4.00.6/4.00.9/4.01.0/4.01.1/4.01.4/4.01.4/4.01.2/4.01.0/4.01.8/4.02.4/4.02.6/4.02.8/4.04.1/4.04.5/4.04.5/4.04.3/4.04.2/4.03.9/4.03.6/4.03.4/4.02.8/4.02.4/4.02.1/4.01.7/4.01.4/4.01.4/4.01.1/4.00.8/4.00.5/4.00.5/4.00.3/4.00.3/4.00.4/4.00.6/4.00.5/4.00.5/4.00.5/4.00.4/4.00.5/4.00.5/4.00.5/4.00.4/4.00.3/4.00.3/4.00.3/4.00.2/4.00.4/4.00.4/4.00.5/4.00.5/4.00.4/4.00.3/4.00.2/4.0
IAM (Identity and Access Management)0.0/4.00.0/4.00.0/4.00.1/4.00.2/4.00.3/4.00.4/4.00.6/4.00.8/4.00.9/4.01.0/4.01.2/4.01.7/4.01.9/4.02.3/4.02.3/4.01.6/4.01.6/4.01.8/4.02.2/4.02.0/4.01.6/4.01.7/4.02.2/4.02.2/4.01.6/4.01.3/4.01.1/4.01.0/4.01.0/4.00.7/4.00.7/4.01.0/4.00.8/4.00.6/4.00.6/4.00.4/4.00.4/4.00.5/4.00.7/4.00.6/4.00.6/4.00.6/4.00.6/4.00.6/4.00.6/4.00.7/4.00.6/4.00.4/4.00.3/4.00.3/4.00.3/4.00.4/4.00.5/4.00.5/4.00.5/4.00.5/4.00.4/4.00.2/4.0
Telecomm Ops (Telecommunications Operations)0.0/4.00.0/4.00.0/4.00.1/4.00.1/4.00.1/4.00.3/4.00.3/4.00.4/4.00.4/4.00.6/4.00.7/4.00.7/4.00.4/4.01.0/4.01.3/4.01.3/4.01.4/4.02.0/4.02.3/4.02.3/4.02.0/4.02.1/4.02.1/4.02.7/4.01.7/4.01.5/4.01.2/4.01.0/4.00.9/4.00.7/4.00.7/4.00.5/4.00.6/4.00.2/4.00.4/4.00.2/4.00.1/4.00.1/4.00.2/4.00.2/4.00.2/4.00.2/4.00.4/4.00.2/4.00.2/4.00.4/4.00.3/4.00.2/4.00.2/4.00.1/4.00.1/4.00.1/4.00.1/4.00.1/4.00.2/4.00.4/4.00.3/4.00.1/4.0
< 50%50–85%85–100%100–125%> 125%

Portfolio Gantt (post-solve)

ProjectShiftJan 26Feb 26Mar 26Apr 26May 26Jun 26Jul 26Aug 26Sep 26Oct 26Nov 26Dec 26Jan 27Feb 27Mar 27Apr 27May 27Jun 27Jul 27Aug 27Sep 27Oct 27Nov 27Dec 27Jan 28Feb 28Mar 28Apr 28May 28Jun 28Jul 28Aug 28Sep 28Oct 28Nov 28Dec 28Jan 29Feb 29Mar 29Apr 29May 29Jun 29Jul 29Aug 29Sep 29Oct 29Nov 29Dec 29Jan 30Feb 30Mar 30Apr 30May 30Jun 30Jul 30Aug 30Sep 30Oct 30Nov 30
BS055INTAPP Time Capture (Pilot)
Prio 1 · ASAP
0
Initiating
BS047INTAPP Time Capture POC
Prio 2 · must-start 2026-08
0
Initiating
BS011Elite 3E Saas Cloud Implementation
Prio 3 · must-start 2026-01
0
Initiating
BS012Coupa Expense Management
Prio 3 · ASAP
0
Initiating
BS013Time Entry of the Future Assesment
Prio 3 · ASAP
0
Initiating
BS026HCM System Selection
Prio 3 · ASAP
0
Initiating
BS027HCM Implementation
Prio 3 · ASAP
0
Initiating
Planning
BS035Panapto (or MS Streams) Implementation (Includes Software License Costs)
Prio 3 · ASAP
0
Initiating
BS060Atllis
Prio 3 · ASAP
0
Initiating
Executing
BS061Matter Intake K&E (MIKE) Phase 3
Prio 3 · ASAP
0
Initiating
BS064Time Entry of the Future Implementation
Prio 3 · ASAP
0
Initiating
BS065Migrate Atlassian Jira to the Cloud
Prio 3 · must-finish 2027-10
0
Initiating
BS066Elite Upgrade 2027
Prio 3 · must-finish 2027-06
0
Initiating
RE011Miami Office Buildout Phase 2 (Floors 34 & 35)
Prio 3 · must-start 2026-03
0
Initiating
RE023Houston AV Refresh
Prio 3 · ASAP
0
Initiating
Planning
RE041Nashville Office Build Out & Relocation
Prio 3 · must-start 2026-05
0
Initiating
RE050Chicago Conference Densification
Prio 3 · ASAP
0
Initiating
RE051Chicago Corner Retreats
Prio 3 · ASAP
0
Initiating
RE052Chicago Innovation Suite
Prio 3 · ASAP
0
Initiating
RE053Chicago Lounge Entry Furniture
Prio 3 · ASAP
0
Initiating
RE054Brussels Expansion
Prio 3 · ASAP
0
Initiating
RE055Shanghai Build Out & Relocation
Prio 3 · ASAP
0
Initiating
RE056Tokyo Office Built Out & Relocation
Prio 3 · ASAP
0
Initiating
RE057New York 900 Build Out Phase 2
Prio 3 · must-start 2026-09
0
Initiating
RE059New York 55th Floor Decommission
Prio 3 · must-finish 2028-01
0
Initiating
RE060New York 601LX 49th Floor Double Associate Office Conversion
Prio 3 · ASAP
+2
Initiating
RE061New York 601LX 32nd Floor Full Floor Refresh Build Out
Prio 3 · ASAP
+6
Initiating
RE062New York 601LX 37th Floor Finance Area Workstation Infill
Prio 3 · ASAP
+8
Initiating
RE063New York 601LX 56th Floor Full Floor Refresh Build Out
Prio 3 · ASAP
+8
Initiating
RE064New York 601LX 51st Floor AV Upgrades
Prio 3 · ASAP
+6
Initiating
RE065DC Office Densification Phase 2
Prio 3 · ASAP
+6
Initiating
RE066DC AV Upgrades Phase 2
Prio 3 · ASAP
+9
Initiating
RE067Boston Double Associate Infill & Space Upgrade
Prio 3 · ASAP
+9
Initiating
RE068Boston Floor 53 Decommission
Prio 3 · ASAP
+7
Initiating
RE070Nashville Office Decommission (150 3rd Ave)
Prio 3 · must-finish 2027-09· INFEASIBLE
0
Initiating
RE071LA Century City MPR Expansion
Prio 3 · ASAP
+9
Initiating
RE072San Francisco 29th Floor AV Upgrade
Prio 3 · ASAP
+8
Initiating
RS003Emergency Notification Solution
Prio 3 · must-start 2026-08
0
Initiating
RS005Risk Platform Design
Prio 3 · must-finish 2028-08· INFEASIBLE
+7
Initiating
RS010Risk Platform Implementation
Prio 3 · must-finish 2028-08· INFEASIBLE
+14
Initiating
RS012CLE Compliance Evaluation
Prio 3 · must-finish 2025-12· INFEASIBLE
0
Initiating
RS036Veza Identity Lifecycle Management Implementation
Prio 3 · must-start 2026-07· INFEASIBLE
0
Initiating
RS043Application Allowlisting for Laptops
Prio 3 · must-start 2026-06
0
Initiating
RS045SIEM Replacement - Implementation (Phase 2)
Prio 3 · must-start 2026-04
0
Initiating
Executing
RS046Implement Network Detection & Response
Prio 3 · must-start 2026-07
0
Initiating
RS081Insider Risk Detection for iManage
Prio 3 · ASAP
+5
Initiating
Closing
RS084Move Cisco Umbrella Dashboard to Secure Web Gateway
Prio 3 · must-finish 2027-09· INFEASIBLE
0
Initiating
RS087FINRA Implementation
Prio 3 · ASAP
+9
Initiating
RS088Walls Detangle
Prio 3 · must-finish 2030-08
0
Initiating
RS102ITAR data separation assessment
Prio 3 · ASAP
0
Initiating
IT023Starfish APAC Automation
Prio 3 · must-start 2026-07· INFEASIBLE
0
Initiating
IT025SPO Bulk Content Retention and Bulk Notification Implementation
Prio 3 · ASAP
+9
Initiating
IT030Procurement Datamart
Prio 3 · ASAP
+6
Initiating
IT049Avaya Gateway Hardware Refresh
Prio 3 · must-finish 2026-06· INFEASIBLE
0
Initiating
IT055Purview Data Governance Operationalization - Phase 1
Prio 3 · ASAP
+11
Initiating
Executing
IT065Apple Mobile Device Onboarding Redesign
Prio 3 · must-start 2026-09· INFEASIBLE
0
Initiating
IT074NexThink Implementation
Prio 3 · ASAP
+13
Initiating
Executing
IT078SDWAN - Prod Deployment
Prio 3 · ASAP
+11
Initiating
IT079Wireless Access Point Refresh - Phase 2.
Prio 3 · must-finish 2027-10· INFEASIBLE
0
Initiating
IT086Matter Intake K&E Phase 2
Prio 3 · must-start 2026-09· INFEASIBLE
0
Initiating
IT096MDM Pilot — Build and Evaluation
Prio 3 · ASAP
+15
Initiating
Executing
IT097MDM Phase 2
Prio 3 · ASAP
+15
Initiating
IT098Critical Metrics Inventory and Definitions
Prio 3 · ASAP
0
Initiating
IT100Integration Platform Rationalization
Prio 3 · ASAP
+8
Initiating
Executing
IT105RHEL 8.x End of Life
Prio 3 · must-finish 2029-04· INFEASIBLE
0
Initiating
IT108Server 2019 End Of Life
Prio 3 · must-finish 2028-12· INFEASIBLE
0
Initiating
Deploying
IT129Knowledge Management Datamart
Prio 3 · ASAP
+14
Initiating
IT130Risk Management Datamart
Prio 3 · ASAP
+15
Initiating
Executing
IT133Azure AI API Gateway
Prio 3 · must-start 2026-10· INFEASIBLE
0
Initiating
IT134AI-Ready Data Foundation
Prio 3 · ASAP
+18
Initiating
IT135New EAI platform(Mulesoft replacement)
Prio 3 · ASAP
+18
Initiating
PI007DeepJudge PoC (change name to Pilot)
Prio 3 · must-start 2026-01
0
Initiating
PI032Legal (Litigation) Case Management Tool Assessment
Prio 3 · ASAP
0
Initiating
Planning
PI033Syllo
Prio 3 · ASAP
+21
Initiating
PI040DeepJudge Production Deployment
Prio 3 · ASAP
+24
Initiating
PI044Syllo Phase 2
Prio 3 · ASAP
+22
Initiating
PI050Tribe DealOS
Prio 3 · must-start 2026-02· INFEASIBLE
0
Initiating
PI057AI Pods
Prio 3 · must-start 2026-05· INFEASIBLE
0
Initiating
PI063Orbital Implementation
Prio 3 · ASAP
+21
Initiating
PI066Agent365
Prio 3 · ASAP
+24
Initiating
PI073Centari
Prio 3 · ASAP
+21
Initiating
PI074Innovation Engineering Builds
Prio 3 · ASAP
+27
Initiating
PI075Crane Patents
Prio 3 · ASAP
+30
Initiating
PI077Ground Truth Intelligence
Prio 3 · ASAP
+32
Initiating
PI078OurFirm
Prio 3 · ASAP
+26
Initiating
PI079HSR 4(c/d) review build
Prio 3 · must-finish 2028-01· INFEASIBLE
0
Initiating
PI080Transcript Management Solution build out
Prio 3 · ASAP
+29
Initiating
PI081Tackle.ai
Prio 3 · ASAP
+28
Initiating
PI082Patlytics
Prio 3 · ASAP
+24
Initiating
PI083GRII White Collar
Prio 3 · ASAP· INFEASIBLE
+34
Initiating
PI085Visual Ping
Prio 3 · ASAP
+37
Initiating
PI086KE Disconnect (Esentio)
Prio 3 · must-finish 2028-01· INFEASIBLE
0
Initiating
PI091Palantir Phase 2
Prio 3 · ASAP· INFEASIBLE
+34
Initiating
PI092Theo Phase 2
Prio 3 · ASAP
+38
Initiating
PI094Practice Innovation Chargeback Tool
Prio 3 · ASAP
+42
Initiating
PI095Debt Finance Portal Implementation Project
Prio 3 · ASAP· INFEASIBLE
+34
Initiating
PI096Firecrawl API Solution Implementation
Prio 3 · ASAP
+25
Initiating
IT083Cloud Governance for AI Workloads
Prio 4 · ASAP· INFEASIBLE
+38
Initiating
RS006iCompli Implementation Phase 3
Prio 5 · must-finish 2025-12· INFEASIBLE
0
Initiating

Infeasible projects (23)

Hard constraints (capacity within horizon, must-start, must-finish, or dependency) cannot be satisfied.

  • RE070 Nashville Office Decommission (150 3rd Ave)
    No shift within must-finish (2027-09) clears all role capacity conflicts. Bottleneck: Network Ops in 2027-08 — short 0.11 FTE.
  • RS005 Risk Platform Design
    No shift within must-finish (2028-08) clears all role capacity conflicts. Bottleneck: Network Ops in 2027-10 — short 0.01 FTE.
  • RS010 Risk Platform Implementation
    Finish (2030-03) is past must-finish (2028-08).
  • RS012 CLE Compliance Evaluation
    Finish (2027-04) is past must-finish (2025-12).
  • RS036 Veza Identity Lifecycle Management Implementation
    Must-start 2026-07 conflicts with role capacity; solver isn't allowed to shift. Bottleneck: Network Ops in 2027-08 — short 0.21 FTE.
  • RS084 Move Cisco Umbrella Dashboard to Secure Web Gateway
    No shift within must-finish (2027-09) clears all role capacity conflicts. Bottleneck: Network Ops in 2027-08 — short 0.21 FTE.
  • IT023 Starfish APAC Automation
    Must-start 2026-07 conflicts with role capacity; solver isn't allowed to shift. Bottleneck: OCM (Organizational Change Management) in 2027-01 — short 0.37 FTE.
  • IT049 Avaya Gateway Hardware Refresh
    No shift within must-finish (2026-06) clears all role capacity conflicts. Also: Finish (2027-05) is past must-finish (2026-06). Bottleneck: OCM (Organizational Change Management) in 2027-01 — short 0.46 FTE.
  • IT065 Apple Mobile Device Onboarding Redesign
    Must-start 2026-09 conflicts with role capacity; solver isn't allowed to shift. Bottleneck: OCM (Organizational Change Management) in 2027-01 — short 0.87 FTE.
  • IT079 Wireless Access Point Refresh - Phase 2.
    No shift within must-finish (2027-10) clears all role capacity conflicts. Bottleneck: OCM (Organizational Change Management) in 2027-04 — short 0.03 FTE.
  • IT086 Matter Intake K&E Phase 2
    Must-start 2026-09 conflicts with role capacity; solver isn't allowed to shift. Bottleneck: OCM (Organizational Change Management) in 2026-12 — short 0.05 FTE.
  • IT105 RHEL 8.x End of Life
    No shift within must-finish (2029-04) clears all role capacity conflicts. Bottleneck: OCM (Organizational Change Management) in 2027-04 — short 0.11 FTE.
  • IT108 Server 2019 End Of Life
    No shift within must-finish (2028-12) clears all role capacity conflicts. Bottleneck: OCM (Organizational Change Management) in 2027-04 — short 0.13 FTE.
  • IT133 Azure AI API Gateway
    Must-start 2026-10 conflicts with role capacity; solver isn't allowed to shift. Bottleneck: OCM (Organizational Change Management) in 2026-12 — short 0.41 FTE.
  • PI050 Tribe DealOS
    Must-start 2026-02 conflicts with role capacity; solver isn't allowed to shift. Bottleneck: OCM (Organizational Change Management) in 2026-12 — short 0.66 FTE.
  • PI057 AI Pods
    Must-start 2026-05 conflicts with role capacity; solver isn't allowed to shift. Bottleneck: OCM (Organizational Change Management) in 2026-10 — short 0.19 FTE.
  • PI079 HSR 4(c/d) review build
    No shift within must-finish (2028-01) clears all role capacity conflicts. Bottleneck: OCM (Organizational Change Management) in 2027-05 — short 1.39 FTE.
  • PI083 GRII White Collar
    No shift within the planning horizon clears all role capacity conflicts. Bottleneck: OCM (Organizational Change Management) in 2030-03 — short 0.12 FTE.
  • PI086 KE Disconnect (Esentio)
    No shift within must-finish (2028-01) clears all role capacity conflicts. Bottleneck: OCM (Organizational Change Management) in 2027-08 — short 0.39 FTE.
  • PI091 Palantir Phase 2
    No shift within the planning horizon clears all role capacity conflicts. Bottleneck: OCM (Organizational Change Management) in 2029-12 — short 0.07 FTE.
  • PI095 Debt Finance Portal Implementation Project
    No shift within the planning horizon clears all role capacity conflicts. Bottleneck: OCM (Organizational Change Management) in 2030-03 — short 0.51 FTE.
  • IT083 Cloud Governance for AI Workloads
    No shift within the planning horizon clears all role capacity conflicts. Bottleneck: OCM (Organizational Change Management) in 2030-11 — short 0.45 FTE.
  • RS006 iCompli Implementation Phase 3
    No shift within must-finish (2025-12) clears all role capacity conflicts. Also: Finish (2028-04) is past must-finish (2025-12). Bottleneck: OCM (Organizational Change Management) in 2027-05 — short 1.55 FTE.