IT049Avaya Gateway Hardware Refresh
Details
This project has a pattern selected. Click regenerate to (re)build phases + role demand from the pattern — this replaces current phases, demand, and any manual FTE adjustments.
Phases & role demand
Initiating2026-12-01 → 2026-12-14
Role demand (FTE)
Planning2026-12-15 → 2027-01-12
Role demand (FTE)
Executing2027-01-13 → 2027-03-30
Role demand (FTE)
Deploying2027-03-31 → 2027-04-25
Role demand (FTE)
Closing2027-04-26 → 2027-05-21
Role demand (FTE)
Dependencies
Predecessor projects that constrain when this project can start or finish.
FS finish-to-start (default) · SS start-to-start · FF finish-to-finish · SF start-to-finish. Lag is in months (negative = lead).
None.