RS081Insider Risk Detection for iManage
Details
This project has a pattern selected. Click regenerate to (re)build phases + role demand from the pattern — this replaces current phases, demand, and any manual FTE adjustments.
Phases & role demand
Initiating2027-07-15 → 2027-07-30
Role demand (FTE)
Planning2027-07-31 → 2027-09-02
Role demand (FTE)
Executing2027-09-03 → 2027-12-01
Role demand (FTE)
Deploying2027-12-02 → 2027-12-31
Role demand (FTE)
Closing2028-01-01 → 2028-01-31
Role demand (FTE)
Dependencies
Predecessor projects that constrain when this project can start or finish.
FS finish-to-start (default) · SS start-to-start · FF finish-to-finish · SF start-to-finish. Lag is in months (negative = lead).
None.